Robert Gullium Ranch
This system was designed and engineered in conjunction with Salt River Project from Phoenix, Arizona. The system was delivered on an 18 foot trailer and placed on the piers by a crane. The system was pre-wired at our facility and ready for immediate installation upon arrival at the site. Electricity was supplied to the Gullium Ranch within two hours of placement of the skid system.
Components of System:
|
1
|
Custom engineered skid system
|
|
4
|
Direct Power and Water RGM8-SR90 racks
|
|
2
|
Direct Power and Water insulated battery enclosure for 16
L-16 batteries
|
|
32
|
US Battery L16 375 amp hour batteries
|
|
1
|
Trace SW4024 inverter
|
|
2
|
Trace C40 charge controller
|
|
1
|
Campbell Data Logging equipment
|
|